Physical and Financial Progress Report(Revenue & Land Reforms Dptt.)


Sl.No.Name Of the WorkDistrictAmount of Administrative Approval(In Rs.)Date Of Start/CompletionExpenditure Till March 2017(In Rs.)Expenditure in 2017-18(In Rs.)Cumulative Expenditure till date (2017-18)(In Rs.)Physical Progress In %
1 Const. of court office of the Deputy district magistrate at divisional office masaudhiID:(6621) Patna Ref No.:314Amount.: 2989000Dated.:10-Oct-2014 09-Sep-2015/ 08-Mar-2016 2555232.00 290444.00 2845676.00 100
2 Const. of court office room of deputy district magistrate at divisional office DanapurID:(6622) Patna Ref No.:314(8)Amount.: 2989000Dated.:10-Oct-2014 25-Feb-2015/ 24-Aug-2015 2670238.00 405664.00 3075902.00 100
3 Const of court room office of deputy district magistrate of divisional office of buxar sadarID:(6746) Buxur Ref No.:314Amount.: 2989000Dated.:10-Oct-2014 10-Jan-2015/ 09-Jul-2015 2011566.00 1000000.00 3011566.00 100
4 Construction of D.C.L.R. Building Gaya, Distt - GayaID:(6281) Gaya Ref No.:1376Amount.: 29.89Dated.:29-Nov-2013 17-Mar-2014/ 16-Sep-2014 0.00 0.00 0.00
5 Construction of D.C.L.R. Building, Sherghatty, Distt - GayaID:(5301) Gaya Ref No.:1376Amount.: 2989000.00Dated.:29-Nov-2013 03-03-2014/ 02-09-2014 2400000.00 0.00 2400000.00 100
6 Construction of DCLR building at Jehanabad, Dist - JehanabadID:(6282) Jahanabad Ref No.:314(8)Amount.: 29.89Dated.:10-Oct-2014 29-Jan-2015/ 28-Jul-2015 2308099.00 116250.00 2424349.00 100
7 ConstructConstruction of DCLR Court Building at NaugachiaID:(6138) Bhagalpur Ref No.:314(8)Amount.: 2989000Dated.:10-Oct-2014 11-06-2015/ 10-12-2015 3023445.00 0.00 3023445.00 100
8 Construction of DCLR Building at BhagalpurID:(5530) Bhagalpur Ref No.:55(8)Amount.: 2989000Dated.:29-Nov-2013 15-04-2014/ 14-10-2014 2356480.00 0.00 2356480.00 100
9 Construction of DCLR building at JamuiID:(5311) Jamui Ref No.:1376Amount.: 2989000Dated.:29-Nov-2013 18-03-2014/ 17-09-2014 2290355.00 209051.00 2499406.00 100
10 Construction of DCLR building at KhagariaID:(5312) Khagaria Ref No.:1376Amount.: 2989000Dated.:29-Nov-2013 19-04-2014/ 18-10-2014 2749394.00 284206.00 3033600.00 100
11 Construction of DCLR Building at ShekhpuraID:(6187) Shekhpura Ref No.:3148Amount.: 2989000Dated.:14-Oct-2014 04-Sep-2015/ 03-Mar-2016 2670188.00 262326.00 2932514.00 100
12 D.C.L.R Court Building KishanganjID:(5448) Kishanganj Ref No.:1376Amount.: 2989000Dated.:29-Nov-2013 03-Mar-2014/ 02-Sep-2014 2495638.00 0.00 2495638.00 100
13 Constution of D.C.L.R ,DALSINGHSARAIID:(5905) Samastipur Ref No.:314(8)Amount.: 2989000.00Dated.:10-Oct-2014 29-Jan-2015/ 28-Jul-2015 3010997.00 0.00 3010997.00 100
14 Constution of D.C.L.R ,ROSARAID:(5906) Samastipur Ref No.:314(8)Amount.: 3291000.00Dated.:10-Oct-2014 29-Jan-2015/ 28-Jul-2015 2990006.00 0.00 2990006.00 100
15 Constution of D.C.L.R ,SAMASTIPURID:(5922) Samastipur Ref No.:314(8)Amount.: 2989000.00Dated.:10-Oct-2014 10-Mar-2015/ 09-Sep-2015 2381715.00 0.00 2381715.00 100
16 Constution of D.C.L.R ,BENIPATTIID:(5903) Madhubani Ref No.:1376Amount.: 3291000.00Dated.:29-Nov-2013 03-Mar-2014/ 02-Sep-2014 2795476.00 0.00 2795476.00 100
17 Construction of D.C.L.R. Court Building Sheohar Dist.-Sheohar.ID:(6357) Sheohar Ref No.:314 (8)Amount.: 2989000Dated.:10-Oct-2014 20-May-2015/ 19-Nov-2015 2848275.00 89565.00 2937840.00
     41557104.002657506.0044214610.00