Physical and Financial Progress Report(Seed Certification Agency)


Sl.No.Name Of the WorkDistrictAmount of Administrative Approval(In Rs.)Date Of Start/CompletionExpenditure Till March 2016(In Rs.)Expenditure in 2016-17(In Rs.)Cumulative Expenditure till date (2016-17)(In Rs.)Physical Progress In %
1 Regional office at kudraID:(6628) Kaimur Ref No.:2586Amount.: 11200000Dated.:13-Oct-2014 25-Apr-2015/ 24-Apr-2016 6888914.00 0.00 6888914.00 100
2 Construction of Bihar State Seed Certification Centre at BhagalpurID:(6145) Bhagalpur Ref No.:2586Amount.: 11200000Dated.:13-Oct-2014 13-05-2015/ 12-05-2016 7019972.00 233061.00 7253033.00 90
3 Construction of Bihar State Seed Certification Agency at Mushahari, Dist.- Muzaffarpur.ID:(6356) Muzaffarpur Ref No.:2586Amount.: 11200000Dated.:13-Oct-2014 20-May-2015/ 19-May-2016 8270621.00 0.00 8270621.00 100
     22179507.00233061.0022412568.00 